credit cards

800.890.7325

After Hours Emergency

800.876.6173


Bar

CASE STUDIES:




48" Diameter Sewage Pump Impeller


Problem:


The impeller for one of N.Y.C. main sewage pumps was found "Practically Destroyed".


Possible Solutions:

• Get a new impeller from the manufacturer. This involved a waiting period of 48 - 52 weeks, a good long term
solution, which meant having the pump out of service for (1) one year.


• Call in several vendors so that they could offer a more viable solution. Every vendor practically gave up;
saying that since more than half of the impeller was missing, there was nothing that could be done.


Frontline’s Solution:

Rebuild the impeller as close as possible to the original dimension. The customer provided Frontline with a drawing
of the impeller and we went to work. See detailed description below.

impeller 1
impeller 2
impeller 3
impeller 4

This is what was left over

of the 48"

diameter impeller.

We had a foundry cast a

ring and set it at the

right height following

a customer's

dimensional drawing.

Following the existing

profile, we built a vane

made out of reinforced plaster. Then we cut out the

vane and sent it to a

foundry to be reproduced.


The foundry cast

(4) four identical vanes

(2-shown in photo).

impeller 5
impeller 6
impeller 7
impeller 8

We then trimmed off

the existing impeller

vanes uniformly.

The (4) four new vanes

were carefully set in place

and welded to the ring

and to the hub.

The I.D. and O D. of the

suction ring was then machined according to the manufacturer's specifications.

The impeller was then put thru an extensive phase of hand grinding to bring the

(4) four vanes to a uniform and dimensionally

symmetric profile.

impeller 9
impeller 10
impeller 11
impeller 12

A stainless steel wear ring was then "shrunk on" and

pinned to the impeller.

The impeller was

then secured to a shaft

provided by the customer.

Impeller and shaft assembly being lifted and secured

onto the balancing machine.

Operator getting ready

to dynamically balance

the rotor.

The Results Were:


The entire job took only 5 1/2 weeks, allowing the customer to put a very important piece of equipment
back on line at a fraction of the original cost estimate, and with a much shorter downtime than originally anticipated.

Frontline Industries, Inc. | 990 Chancellor Avenue | Irvington NJ 07111 | 800.890.7325 | e-mail: info@frontlineindustries.com

© 2011 Frontline Industiries Inc.